What to Know About Using Drones for Site Monitoring and Documentation

Drones have gone from “cool toy” to everyday tool on job sites faster than any technology I’ve seen in my 15+ years around builders, surveyors, and developers. The crews that use them well aren’t flying for fun—they’re saving time, protecting margins, and settling disputes before they turn into claims. If you’re considering drones for site monitoring and documentation—or you’re trying to level up an existing program—this guide walks you through what works in the field, what to avoid, and how to get real value without bogging your team down.

Why Builders and Developers Are Leaning on Drones

Drones don’t replace surveyors or superintendents. They augment them. The real payoff shows up in three places:

  • Faster, clearer documentation. A single 15-minute flight can create a high-resolution aerial map of the entire site. Compare it week-to-week, and schedule slips or grading changes jump out.
  • Fewer disputes. When an owner, neighbor, or sub questions a change, you’ve got time-stamped imagery, measurements, and models. No “he said/she said.”
  • Better planning. Orthomosaics and 3D models give project managers, estimators, and VDC teams a current, shared view of reality. It’s like having a living as-built.

Here are typical wins I’ve seen:

  • Earthwork contractor cut rework by 25% on a 40-lot subdivision by comparing drone surfaces against design every Friday. They caught a mis-set grade stake in week two, not week eight.
  • GC reduced monthly progress photo walks from eight hours to two, then used side-by-side aerials to settle a $38k paving quantity dispute—without lawyers.
  • Developer accelerated sales by overlaying colored lot lines and utility locations on an aerial for buyers and city staff. Instant clarity.

What You Can Capture and Produce

Think beyond “cool photos.” Modern drones capture structured data that translates into measurable deliverables.

Orthomosaics (Georeferenced Aerial Maps)

  • What it is: A stitched, top-down map with consistent scale, georeferenced to real-world coordinates.
  • Where it shines: Tracking progress, documenting trench locations, annotating site logistics, and communicating with stakeholders.
  • Useful formats: GeoTIFF for CAD/GIS; KMZ for quick viewing in Google Earth; web viewers in DroneDeploy, Pix4Dcloud, or Propeller.

3D Models and Point Clouds

  • What it is: Dense 3D reconstruction from hundreds of overlapping photos.
  • Where it shines: Facade mapping, volume calculations, stockpiles, walls, retaining systems, and clash reviews against BIM.
  • Formats: LAS/LAZ point clouds, OBJ/FBX meshes, DXF contours. Most CAD/BIM tools accept these.

Digital Surface Models (DSM) and Contours

  • What it is: Elevation data representing ground plus objects (machines, stockpiles, buildings).
  • Where it shines: Cut/fill analysis, grading checks, drainage planning.
  • Tip: To approximate bare earth, run ground classification to remove equipment/vegetation from the surface before generating contours.

Stockpile Volumes

  • Typical accuracy: ±1–2% with RTK and well-defined pile bases; ±3–5% without controls.
  • Use cases: Asphalt, aggregate, topsoil inventories for billing and month-end reporting.

Thermal Imaging

  • What it is: Heat signature data from an IR camera.
  • Where it shines: Roof moisture investigations, envelope leaks, solar array hot spots, checking radiant heating circuits.
  • Caveat: Thermal work is technique-sensitive—plan flights around sunrise/sunset or after rainfall for roof moisture mapping.

LiDAR (For Vegetation or Complex Terrain)

  • What it is: Laser scanning from the air penetrates some vegetation to reach ground, producing highly accurate elevation data.
  • Where it shines: Heavily treed sites, utility corridors, steep slopes, and pre-grading surveys where photogrammetry struggles.
  • Budget reality: Expect $25k–$75k+ for hardware, or outsource per project.

Hardware: Choosing the Right Drone for the Job

You don’t need a $30k rig to get good results. Match the tool to your needs and budget.

Entry-Level Mapping (Great for Progress, General Mapping)

  • Examples: DJI Air 3, Mavic 3 Classic (not RTK), Autel Evo Lite
  • Budget: $1,000–$2,000
  • Pros: Affordable, easy to fly, great for visuals and basic mapping.
  • Cons: No RTK; accuracy relies on Ground Control Points (GCPs). Not ideal for tight tolerances.

RTK/PPK Mapping Drones (The Construction Sweet Spot)

  • Examples: DJI Mavic 3 Enterprise RTK, DJI Phantom 4 RTK (used), Autel EVO II RTK, Parrot Anafi AI RTK
  • Budget: $3,500–$9,000 new
  • Pros: Centimeter-level positioning without heavy reliance on GCPs; reliable mapping cameras; long flight times (30–45 min).
  • Cons: Still need occasional GCPs/checkpoints for QA; wind/EMI can challenge smaller airframes.

Heavy-Lift or Modular Platforms (LiDAR, Thermal, Multispectral)

  • Examples: DJI Matrice 350 RTK with Zenmuse L1 LiDAR or H20T thermal, Skydio X2E, Freefly Alta (specialty)
  • Budget: $10,000–$40,000+ (payload-dependent)
  • Pros: Flexible sensors, rugged, high accuracy, enterprise-grade safety features.
  • Cons: Cost, training needs, larger footprint, more complex compliance.

What Camera Specs Actually Matter

  • Sensor size and pixel size: Larger sensors/pixels handle low light better and reduce noise. For mapping, 20 MP 1″ sensors are a good baseline.
  • Mechanical shutter: Prevents rolling-shutter distortions during fast flights—key for mapping accuracy.
  • RTK/PPK: Onboard positioning that ties each photo to a centimeter-level coordinate.
  • Shutter speed control: You want 1/800–1/1000 second or faster for mapping to avoid motion blur.

Batteries and Power

  • Flight time: Realistic 20–35 minutes per battery (wind and payload matter).
  • Field charging: Inverter generator or 1000–2000W portable power station. Keep a fire-resistant LiPo bag on hand.
  • Battery care: Label batteries, track cycles, retire swollen packs, store at 30–50% charge, keep warm in winter (insulated case, hand warmers).

Rules and Approvals: Navigating Compliance Without Headaches

Regulations vary by country. Here’s the quick-start for the U.S., with notes for other regions.

United States (FAA Part 107)

  • License: Part 107 Remote Pilot Certificate. Study ~10–20 hours; test fee ~$175 at an FAA-approved center. Recurrent training is now free online.
  • Airspace: Use LAANC for near-instant authorization in controlled airspace (Class B/C/D/E). Stay at or below approved grid altitudes.
  • Remote ID: Required for most drones as of 2024. Verify your aircraft has built-in Remote ID or add a module ($100–$300).
  • Operations over people: Allowed only with Category 1–4 compliant drones or with special waivers. Most construction flights should avoid flying directly over workers.
  • Night operations: Permitted with Part 107 training and anti-collision lights visible for 3+ miles. Adjust camera settings to avoid blurry imagery.
  • Visual line of sight (VLOS): Required unless you have a BVLOS waiver (rare in construction).
  • Waivers: Common ones include beyond VLOS, operations over people, and certain airspace restrictions—most projects don’t need waivers if planned well.

Practical move: Coordinate with your safety manager. Some GCs add UAS to the site-specific safety plan and require pilots to sign in/out and brief the superintendent before flights.

Canada (Transport Canada)

  • Basic vs. Advanced pilot certificate depending on proximity to people and airspace; registration required.
  • Advanced ops often require RPAS flight review and manufacturer safety declaration.

EU/UK (EASA/CAA)

  • EU: Open category (A1/A2/A3) for low-risk; Specific category for higher risk via SORA; class-marked drones (C0–C4) matter.
  • UK: Similar structure; PDRA01 common for certain operations; A2 CofC useful for closer-to-people work.

Wherever you operate, confirm local privacy and data protection laws, especially for residential areas.

Insurance, Contracts, and Risk

  • UAS liability insurance: Often required by GCs and owners. Typical limits: $1M–$5M; premiums $600–$1,500/year depending on usage.
  • Hull insurance: Covers your drone equipment from damage or loss.
  • Contract language:
    • Define data ownership and who can share it.
    • Clarify accuracy tolerances per deliverable (e.g., ±5 cm horizontal with RTK and GCPs).
    • Set retention periods (e.g., keep raw data 2 years, processed data 7 years).
    • Include a UAS addendum covering safety, airspace compliance, and privacy.

The Workflow That Works: A Step-by-Step Playbook

1) Plan the Mission

  • Define the question: Progress photos? Stockpile volumes? Pre-pour slab documentation?
  • Choose deliverables: Orthomosaic, DSM, 3D mesh, volume report, thermal overlay, or simply high-res stills.
  • Pick equipment: RTK mapping drone for accuracy; thermal payload for envelope diagnostics.
  • Airspace check: Aloft/FAA DroneZone/LAANC. Verify not within TFRs (wildfires, stadiums).
  • Weather window:
    • Wind under 20 mph (9 m/s) for small drones.
    • Overcast is great for mapping to avoid harsh shadows; avoid rain and fog.
    • Sun angle: Midday reduces long shadows for mapping; golden hour is beautiful for marketing photos.

2) Coordinate on Site

  • Brief the superintendent. Share a 20-minute window when you’ll be overhead and your takeoff/landing zone.
  • Establish a buffer from cranes, tower cranes, and active lifts. Radio comms if cranes are slewing.
  • Place signage: “UAS operations in progress.” Keeps curious folks outside the landing zone.

3) Preflight

  • Batteries at proper temperature and charge; check for swelling.
  • SD cards cleared and formatted. Set camera to manual: ISO 100–200, shutter 1/800+, aperture fixed (as available).
  • Set Return-to-Home (RTH) altitude above the tallest obstacle by at least 50–100 ft.
  • Compass/IMU status good; avoid calibrating near rebar or vehicles—walk to an open area.
  • Verify firmware, Remote ID, and geofencing unlocks if near controlled zones.
  • Place GCPs (if using) before takeoff; ensure they’re visible and not shadowed.

4) Flight Settings for Mapping

  • Overlap: 75–80% frontlap and 70–80% sidelap. For 3D models, add oblique crosshatch flights at 60–70° gimbal angle.
  • Altitude: Set for target ground sampling distance (GSD). For a 20 MP 1″ sensor with 10.26 µm pixel size at 24 mm equivalent:
    • GSD (cm/pixel) ≈ (pixel size in µm × altitude in m) / focal length in mm
    • Rough example: (10.26 × 80) / 8.8 ≈ 93 cm/px? That’s off—let’s do a cleaner example.
    • Practical rule: Mavic 3E at 120 m AGL yields ~2.5–3.5 cm/px. At 60 m, ~1.5–2 cm/px. Use manufacturer GSD tables or mission planners for specifics.
  • Speed: Keep it slow enough to avoid motion blur. 3–6 m/s is typical for high-quality mapping at low altitudes.
  • Shutter: 1/1000 s or faster; increase ISO if needed.
  • RTK: Connect to your base (NTRIP network or base station) and verify fixed solution before starting.
  • Camera angle: -90° (nadir) for mapping; -45° to -65° for oblique detail.

5) Capture

  • Start with a quick manual orbit to spot issues and confirm no birds, kites, or surprise cranes.
  • Run the mapping mission; monitor battery and link quality.
  • If winds are strong aloft, shorten legs and increase overlap.
  • Land with 20–30% battery to keep packs healthy.

6) Ground Control and Checkpoints

  • If you need sub-3 cm accuracy, use GCPs: 5–10 well-distributed points on a 20–30 acre site (corners, center, elevation breaks).
  • Use separate checkpoints (not used in processing) to verify accuracy.
  • Mark targets with high-contrast panels; measure with survey-grade GNSS (Rover or total station).

7) Processing

  • Cloud platforms: DroneDeploy, Pix4Dcloud, Propeller, Trimble Stratus. Fast turnaround, easy sharing, subscriptions from ~$200–$900/month.
  • Desktop software: Agisoft Metashape, Pix4Dmapper, RealityCapture, OpenDroneMap. More control; needs a strong workstation (64–128 GB RAM, modern GPU).
  • Typical processing times: Small site (200–400 photos) takes 30–90 minutes in the cloud; 2–4 hours on desktop depending on hardware.
  • Deliverables: Orthomosaic GeoTIFF, DSM/DTM, contours (0.5–1 ft intervals), point cloud (LAS), 3D mesh (OBJ), KMZ overview, volume reports.

8) QA/QC

  • Check residual errors: RMS under 2–3 cm for RTK with good conditions is common.
  • Compare elevations at checkpoints—document vertical error separately from horizontal.
  • Review for stitching artifacts near uniform surfaces (fresh concrete, water) and at shadow edges.

9) Share and Integrate

  • Share a web link with layers (lot lines, utilities, safety zones).
  • Push snapshots into Procore, Autodesk Construction Cloud/BIM 360, PlanGrid, or Bluebeam sessions.
  • Overlay orthos in CAD/Civil 3D using coordinate systems (state plane, UTM). Confirm georeferencing.

10) Archive and Document

  • Keep raw photos, flight logs, and processed outputs organized by date/version.
  • Minimum retention: raw imagery 2 years; processed deliverables aligned with project record policy (often 7–10 years).
  • Note weather, RTK status, and GCP coordinates in a simple metadata sheet.

Getting Accuracy Right: Practical Tips

  • RTK vs. GCPs: RTK dramatically reduces setup time and improves accuracy, but I still recommend 3–5 checkpoints per flight for critical work. If you’re valuing pay items, you want proof.
  • GSD matters: Aim for 2–3 cm/px when measuring stockpiles or checking slab elevations. For general progress, 3–5 cm/px is fine.
  • Avoid shiny and featureless surfaces: Wet concrete, water, white TPO roofs can cause reconstruction gaps. Increase overlap and add manual obliques.
  • Watch shadows: Deep shadows create false “terrain.” Overcast days produce the most consistent surfaces.
  • Magnetics and cranes: Tower cranes, rebar mats, and powerlines can mess with compasses and GNSS. Launch away from steel and be ready for ATTI-like handling if GPS drops.

Safety on Site: Real-World Considerations

  • People and equipment: Don’t fly directly over active crews or running equipment. Plan routes that skirt working areas.
  • RTH altitude: Set higher than the tallest crane boom with margin. Revisit if crane jacking raises the hook height.
  • Lost-link and failsafes: Test your Return-to-Home behavior in a safe area before mission day.
  • Weather calls:
    • Wind: Many mapping drones do fine up to 18–22 mph (8–10 m/s), but imagery quality drops as gimbal struggles.
    • Cold: Batteries sag. Keep them warm; hover a minute to warm cells before mission.
    • Heat: Hot days shorten flight times; give electronics a break between batteries.
  • Fire safety: Store and transport batteries in a LiPo bag/case; never charge unattended.

Data Processing Tools: What I See Working

  • DroneDeploy: Excellent cloud mapping, quick reports, user-friendly, integrates with Procore. Good for teams and standardization.
  • Pix4D (mapper/cloud): Industry stalwart with deep control. Great for power users and custom pipelines.
  • Agisoft Metashape: Accurate, flexible, cost-effective for desktop processing; great for 3D/heritage-quality models.
  • Propeller Aero/Trimble Stratus: Superb for earthwork and volume workflows with AeroPoints GCPs; common in heavy civil.
  • RealityCapture: Blazing fast on strong GPUs; popular for high-fidelity 3D meshes.
  • OpenDroneMap/WebODM: Solid open-source option if you want full control on your servers.

Workstation specs for desktop mapping: 12–24 core CPU, 64–128 GB RAM, modern NVIDIA GPU (e.g., RTX 4070/4080 or better), fast NVMe storage.

Costs and ROI: What to Budget and How It Pays

Here’s a realistic starting budget for an in-house mapping setup:

  • RTK drone kit (Mavic 3E RTK, extra batteries): $4,000–$6,500
  • GNSS corrections (NTRIP subscription) or small base: $600–$1,500/year or $1,500–$3,000 one-time for a lightweight base
  • Software: $200–$900/month depending on platform and seats
  • Insurance: $600–$1,500/year (liability; hull extra)
  • Training: Part 107 exam $175 per pilot; initial study time 10–20 hours
  • Accessories: Landing pad, LiPo bags, hard cases, high-speed SD cards, portable power—$500–$1,500

Outsourcing typical rates:

  • Basic progress flight and orthomosaic: $250–$600 for small sites; $800–$1,500 for larger/complex.
  • Stockpile volumes with report: $300–$900 depending on number of piles and site access.
  • LiDAR: $3,000–$10,000+ per project depending on acreage and deliverables.

ROI examples I’ve observed:

  • Earthwork verification: Catching a 0.2 ft overfill across a 30,000 sf building pad prevented ~$18k in rework. One flight paid for the quarter.
  • Change order defense: Time-stamped orthos showed site was inaccessible due to utility conflict; GC recovered 4 weather days plus standby—about $26k.
  • Stockpile management: Monthly drone volumes prevented double-hauling and corrected weight tickets—$5k–$12k/month on mid-size sites.

Privacy and Neighbor Relations

Construction sites near neighborhoods can trigger complaints if you don’t manage perceptions.

  • Notify neighbors: A brief letter or email from the GC explaining dates, flight paths, and purposes reduces suspicion.
  • Avoid backyards: Plan flight paths that minimize overflight of adjacent residences. Use geofences.
  • Data minimization: Don’t share raw imagery publicly if it shows neighboring properties. Blur sensitive areas if distributing widely.
  • Signage and transparency: On-site signs and a QR code linking to a short FAQ can diffuse on-the-spot concerns.

Common Mistakes (And How to Avoid Them)

  • Skipping overlap to finish faster: Leads to holes in the model. Stick to 75/70% at minimum; increase overlap for shiny surfaces or complex roofs.
  • No RTK or GCPs for “measurable” maps: If you’re taking measurements, you need controls or RTK. Otherwise, treat it as visual reference only.
  • Flying at the wrong time of day: Long shadows destroy elevation accuracy. For mapping, pick midday or overcast.
  • Ignoring cranes and magnetics: Launching next to a rebar pile sets you up for compass errors. Move 30–50 ft away to a clear spot.
  • Poor battery hygiene: Deep discharges and hot car storage kill packs fast. Track cycles and retire suspect batteries.
  • Treating thermal like normal photography: Without a temperature differential (e.g., after sundown or post-rain), you won’t see roof moisture clearly.

Real-World Scenarios

1) Subdivision Grading: Weekly Progress and Quantities

  • Setup: Mavic 3E RTK, NTRIP corrections, 80 m altitude, 80/70 overlap.
  • Workflow: Fly every Friday at noon; generate orthos, DSM, and weekly cut/fill vs. design.
  • Result: Caught a grading crew working off an outdated PDF—prevented ~12 truckloads of rework soil. Weekly reports sped up pay apps with clear visuals.

2) Tilt-Up Warehouse: Panel Pours and Anchor Verification

  • Setup: RTK mapping plus targeted oblique orbits for wall panel embeds.
  • Deliverables: High-res orthos of slab pre-pours; 3D model post-erection for embed alignment.
  • Result: Documented embed placement and cured slab condition before crane mobilization. When a panel cracked, imagery confirmed a pre-existing cold joint issue and limited GC liability.

3) Multifamily Mid-Rise: Exterior QA and Schedule Tracking

  • Setup: Oblique flights at each floor level, orbiting once per week; combine with ground 360 photos.
  • Deliverables: Orbits stitched into a navigable 3D façade model; annotated punchlist items layered on top.
  • Result: MEP sleeve penetrations misaligned with cladding at two stacks. Early detection saved cutting into fireproofed walls later.

4) Roofing and Insurance Claim: Thermal Survey After Storm

  • Setup: Thermal camera flight 1–2 hours after sunset, 60 m AGL, slow speed, 70/70 overlap.
  • Deliverables: Thermal ortho with flagged hot spots; ground verification with moisture meter.
  • Result: Focused destructive testing on three zones instead of dozens; reduced owner disruption and demonstrated cause-and-origin for the claim.

Integrating Drone Data With Your Construction Stack

  • Procore: Upload orthos and 3D views, create observations linked to map locations, attach to RFIs.
  • Autodesk Construction Cloud/BIM 360: Align orthos with the project coordinate system; overlay with Navisworks/Revit models for reality vs. design.
  • Civil 3D: Bring in GeoTIFFs/contours; perform volume calcs; produce sheets with drone-derived backgrounds.
  • Bluebeam: Markup aerial PDFs, track revisions, issue sheets for field use.

Tip: Standardize file naming. Example: ProjectSiteYYYYMMDDOrthoStatePlaneFIPSzone.tif and ProjectSiteYYYYMMDDPointCloud_NAVD88.laz. Future you will thank present you.

Advanced Topics When You’re Ready

  • PPK workflows: Post-process kinematic positioning for sites with poor cellular coverage; builds on RTK accuracy without live corrections.
  • LiDAR corridors: Utility runs, road widenings, and tree-covered slopes benefit from airborne LiDAR to generate DTM through vegetation.
  • BVLOS pilots: For large linear projects, teams are testing beyond VLOS under waivers and detect-and-avoid systems—still specialized and heavily regulated.
  • Thermal mastery: For flat roofs, log weather conditions, surface materials, time since rain, and temperature deltas. Repeat surveys with consistency for trending.
  • Reality capture for as-builts: Combine drone data with terrestrial laser scanning (TLS) for inside/outside models that are clash-checked against federated BIM.

Neighboring Airspace and Geofencing Gotchas

  • Geofencing: Many drones (DJI especially) require unlocking near airports or sensitive areas. Request unlocks ahead of time and store proof of LAANC or authorization.
  • Temporary Flight Restrictions: Sports stadiums (1 hour before to 1 hour after events), wildfires, VIP visits—check NOTAMs on flight day.
  • Helipads and hospitals: Look for “H” markings nearby; keep altitude conservative and eyes/ears open.

Training Your Team

  • Start with one champion: They pass the Part 107 test, set up procedures, and run pilot projects.
  • Build a playbook: Checklists, mission templates, data naming, and QA routine. Keep it simple and repeatable.
  • Cross-train: At least one backup pilot. Teach basic processing so field folks aren’t stuck waiting on “the drone person.”
  • 30/60/90 plan:
    • 30 days: Buy RTK drone kit, pass Part 107, run two low-risk flights, choose software.
    • 60 days: Establish weekly flights on one project; integrate outputs into Procore/CAD; evaluate accuracy with checkpoints.
    • 90 days: Expand to second site; formalize SOPs; review ROI and adjust cadence and deliverables.

Simple Checklists You Can Copy

Pre-Flight

  • Airspace/authorization verified; NOTAMs checked
  • Weather within limits; wind gusts acceptable
  • Batteries inspected, warm, and labeled
  • SD cards formatted; camera manual settings set
  • RTH altitude set; home point confirmed
  • RTK connected and fixed (if using)
  • GCPs placed/marked (if required)
  • Site brief with superintendent; radios if needed
  • Takeoff/landing zone secured; signage up

In-Flight

  • Maintain VLOS; scan for birds/cranes
  • Monitor battery; land with 20–30% remaining
  • Confirm photo capture cadence; spot-check imagery sharpness mid-mission
  • Split long missions into segments if wind increases

Post-Flight

  • Verify photo count vs. mission plan
  • Backup photos immediately to two locations
  • Document RTK status, weather, anomalies
  • Remove/collect GCPs; lock up batteries
  • Start processing or queue to cloud with project metadata

Frequently Asked Questions

  • How accurate can I get without GCPs?
    • With a good RTK drone and strong GNSS, ±2–3 cm horizontal and ±3–5 cm vertical are common. I still recommend a few checkpoints, especially for pay items.
  • Do I need a surveyor on staff?
    • For legal boundary work—yes, use licensed surveyors. For progress mapping, volumes, and internal decision-making, trained in-house teams work well. Collaborate with your surveyor for controls and QA.
  • Can I fly near an airport?
    • Often, yes, with LAANC authorization and within altitude limits. Plan ahead and keep documentation on hand.
  • What about night flights?
    • Allowed under Part 107 with anti-collision lights and required training. Thermal work often benefits from evening flights.
  • Is the data admissible in disputes?
    • Time-stamped georeferenced imagery is compelling. Chain-of-custody, accuracy documentation, and consistent workflows strengthen your position.

Practical Numbers to Keep Handy

  • Overlap: 75–80% front, 70–80% side; increase to 85/80 for complex surfaces.
  • GSD targets: 2–3 cm/px for measurement work; 3–5 cm/px for general progress.
  • Mapping speed: 20 acres can be covered in 15–25 minutes at 300 ft AGL with a 20 MP camera.
  • Wind: Aim for under 18 mph (8 m/s) for clean mapping; up to 22 mph (10 m/s) is doable but expect lower quality.
  • Batteries: Plan 1 battery per 15–25 acres for mapping at 120 m AGL, depending on wind and overlap.

A Note on Data Security

  • Cloud vs. local: Cloud tools are convenient but review your client’s data policies. Some owners require on-prem or approved vendors.
  • Access control: Limit who can download raw imagery; watermark public PDFs and set expiration on shared links.
  • Sensitive infrastructure: Some clients restrict distribution of detailed orthos showing security features. Get approvals before sharing.

Building a Program That Scales

If you’re managing multiple projects, the challenge isn’t flying—it’s standardization.

  • Standard mission templates per site type (subdivision, vertical build, tenant improvement roof).
  • Consistent deliverables and file names so teams know what to expect.
  • Monthly review: What did the drone flights prevent, accelerate, or reveal? Capture the wins—this maintains buy-in.
  • Keep a spare drone: Downtime costs more than a second airframe sitting in the case.

Final Takeaways You Can Act On This Week

  • Pick a pilot project: One site, once a week, same day/time. Produce an orthomosaic and PDF snapshot for the team meeting.
  • Invest in RTK: The jump in accuracy and speed is worth it for construction. It also reduces your dependence on GCPs.
  • Build a 10-minute briefing routine: Airspace, weather, overlap, RTH altitude, and a quick word with the superintendent.
  • Measure something: Do a stockpile volume or a pad elevation check. Turning imagery into numbers is where value shows up.
  • Document: Save your flight logs and raw images. The day you need to settle a dispute, you’ll be glad you did.

Handled well, drones become a reliable part of your field toolkit—like a total station or a laser level, but with an aerial perspective. Start small, be consistent, and let the data speak for itself.

Matt Harlan

I bring first-hand experience as both a builder and a broker, having navigated the challenges of designing, financing, and constructing houses from the ground up. I have worked directly with banks, inspectors, and local officials, giving me a clear understanding of how the process really works behind the paperwork. I am here to share practical advice, lessons learned, and insider tips to help others avoid costly mistakes and move smoothly from blueprint to finished home.